The New Eastern Terminal Proposal
The Site Selection Process
THE NEW EASTERN TERMINAL PROPOSAL
What's changed - how is the new ET proposal different?
From 1998 to March 2008, Western Power has consistently outlined plans
for an Eastern Terminal substation. This would be constructed in
stages, the first stage being a switchyard requiring 4 hectares of
land. Over time the facility would be developed into a full 20 hectares
for a substation with transformers and additional transmission lines,
as described elsewhere on this site.
In the Western Power workshops in Kalamunda in October 2007, on their
website and in numerous publications, media statements and statements
by the Minister for Energy, it was explained that the purpose of the
Eastern Terminal substation was to serve expected development and meet
growth in demand for power in the metropolitan area. The community was
told that the facility was not specifically for the Hills area.
Suddenly, Western Power has announced that only a switchyard is
required, and that the need for development into a full substation is
extremely unlikely. The reason given is that expected land development
and electricity load forecasts for the Hills region do not indicate the need for a substation. The basis for planning appears to have been dramatically changed.
However, even though a switchyard only requires 4 hectare of land,
Western Power still intends acquiring 20 hectares (the area required
for a full terminal substation).
Top of page
Why has Western Power made this change?
We can only guess. Western Power has offered no rational explanation.
Has Western Power's planning over the past 10 years been wrong? It's
inconceivable that their comprehensive planning could get it this
wrong.
But we can speculate. The community workshops in October 2007 were a
community relations disaster for Western Power. Since then, community
opposition to an Eastern Terminal substation has been fierce. Has
Western Power suddenly changed the purported basis for its planning in
an attempt to abate community opposition?
Top of page
Should we believe Western Power?
NO! Why not?
Over the past ten years Western Power’s flip-flop planning has been
erratic and inconsistent, and appears to be based on unreliable
planning data and assumptions. There has been inconsistency concerning
(a) the need for an Eastern Terminal facility, (b) its location, and
(c) whether it should be a substation or a switchyard.
In summary:
- 1998: Long range planning indicated that the construction of
an Eastern Terminal substation located in Hacketts Gully was necessary.
Extensive negotiations with Hacketts Gully residents ensued.
- 2002:
The 1998 plans were abandoned. “Following a review of the long term
electrical load requirements for the east metropolitan area...a
terminal substation will no longer be required at Location 3897
Mundaring Weir Road, Hacketts Gully. We also have no intention to
acquire an alternative site in areas close to Hacketts Gully...” (9 May
2002 Letter to Hacketts Gully residents from Western Power).
- Mid
2007: The 1998 plans were resurrected. Contrary to the 2002 letter,
Hacketts Gully residents were advised that an Eastern Terminal
substation located in Hacketts Gully was necessary.
- October
2007: Kalamunda community forums were told that of eight available
options, one option (Option 6 – the Eastern Terminal substation) must
be constructed, but its location could be anywhere in a broad study
area east of Kalamunda. The planning basis for the substation was
explained by the Minister as follows: "The Eastern Terminal substation
is proposed as part of the transmission network reinforcement program
to improve power supplies and meet the forecast growth in demand for
electricity within the whole of the Perth metropolitan area".
(Minister's reply on 14/11/07 to questions in the Legislative Assembly).
- 7
February 2008: Media release announced that it had now been determined
that two terminal substations were required: the South East Terminal at
Byford (Option 1) and the Eastern Terminal (Option 6). The Eastern
Terminal substation was now less urgent and would be delayed by four
years, and the South East Terminal substation would be built first.
- 15
May 2008: Revised website states that an Eastern Terminal substation is
not required, but a switchyard is: “current electricity forecasts
indicate that it is extremely unlikely that the switchyard would be
developed into a substation”. The planning basis is changed, and is now
focused on land use in the local area and electricity load forecasts
for the hills region.
Western Power’s Eastern Terminal planning is now totally lacking in credibility and cannot be believed.
Top of page
So why does Western Power need 20 hectares of land?
Good question!
While a switchyard only requires 4 hectares, Western Power wants to
acquire 20 ha of forest – the area required for a 2007-style full blown
substation. In
assessing the proposal, we must assume that a full substation may
eventually be built – even though Western Power say they don’t intend
doing so at this time. Otherwise, why would they wish to acquire 20 ha?
Top of page
Why has Western Power sent their letter to so many people and organisations in Kalamunda, Mundaring and Roleystone?
Western Power’s 2007 proposal for an Eastern Terminal substation had
the potential to result in massive forest clearing (400 hectares or
more) and a web of new transmission lines, which might affect people in
those localities. But most residents were not informed at that time. We
complained about this on your behalf. The result is that Western Power
is starting again and improving their process by expanding the range of
stakeholders contacted.
THE SITE SELECTION PROCESS
Top of page
What is the proposed process?
In essence, there would be four steps:
- Western Power's consultants (ERM) would select a number of
site options within the study area. This selection would be based on
previous research including the analysis of sustainability principles
and constraints. Options would be evaluated in terms of technical,
economic, environmental and social criteria (‘Sustainability
principles’) and ‘feasibility criteria’. Certain areas would be ‘no-go’
areas and excluded from consideration. These include Reservoir
Protection Zones (RPZ), National Parks, a Perth Observatory buffer
area, and a residential property buffer area (but these buffer areas
are not defined).
- ERM would prepare a site options paper showing the identified site options and the reasons for their selection.
- The
site options paper would be made available to stakeholders.
Stakeholders would have 4 weeks to comment. During this 4 week period
‘information sessions’ would be held to explain the sites selected.
- The results would be analysed by Western Power and ERM and a final site selected.
At the conclusion of the process, information sessions would be held to explain the final site decision.
Top of page
What’s wrong with the process?
- Many stakeholders were not involved in the exercise last
year, as they were not invited to the October workshops. Gaining an
understanding of the whole story (the switchyard, planning assumptions,
the gantry, upgrade of the line from Boddington, future developments,
implications for the environment, the landscape, people’s properties
and businesses, etc) is essential before one can sensibly consider
Western Power’s proposals. The site selection paper provides no
information on most of these questions. It is essential that open
information sessions be conducted as soon as possible – certainly
before the closing date for submissions (June 16). Without this, Western Power’s consultation process will be deeply flawed. The
SETS Group understands that such meetings have been avoided by Western
Power as they don’t wish to expose themselves to the community
opposition encountered last year.
- In most cases it will not
be possible for Local Governments and other organisations to respond.
Most have a monthly meeting schedule; a response period of around three
weeks does not enable the matter to be researched, listed on agenda
papers, considered at a scheduled monthly meeting, and a response
prepared. No less than two months is required. The present deadline of
June 16 will automatically exclude many or most organisations,
particularly as the letters to organisations were not received until
May 22 or later.
- A
fundamental flaw is that the proposed process does not apply
sustainability principles to the decision concerning the location of an
Eastern Terminal in the Hills area. The whole process is based
on an extraordinary contradiction: Western Power proposes applying
sustainability criteria to the selection of a site, but only technical
and cost factors were considered for the overall project. Environmental
and social factors have not been considered at all.
In the absence of any consideration of sustainability principles in the
decision to locate an Eastern Terminal in state forest in the study
area, the site selection process is not legitimate. To say that
sustainability principles are important for site selection, but not for
selection of the study area, is absolutely hypocritical.
- Western
Power intends using numerical ratings derived from participants’
responses at the Kalamunda workshops in October 2007. Because those
present were not representative of the full range of stakeholders
Western Power has now approached, and given the way in which each of
the workshops turned into a protest session, the quality of any
numerical data derived from those ratings would be very suspect. To
apply such wonky numerical data to the new exercise would simply be
wrong.
- The Action Group believes that, apart from Hacketts
Gully, there are no other genuine site options. In other words, this
whole “site selection exercise” is a sham. (The evidence for this is
outlined in other sections of this website.)
- Western Power
will receive and analyse people’s comments, “and the site selection
process [will be] adjusted if necessary”. We won’t know what the
community has said. There is no guarantee that community feedback will
genuinely be taken into account. Good practice – and trust – require
that truthful feedback is provided to the community.
- Western
Power has listed the criteria they intend using in the identification
of site options. (Their criteria are listed in Table 3.1 on p 9 of the
site selection paper). Western Power’s criteria do not reflect the
views of the community at the October workshops. It is obvious that
Western Power’s criteria have been devised to suit their intentions.
Their application would render virtually any technically feasible site
in the study area “acceptable” – ie the “impacts” would not be a
problem.
The question is whether the “definitions” of ‘high’, ‘medium’ or ‘low’ impact in this table are reasonable.
There are too many criteria in the list to deal with in detail. The following are the most important:
(a) Water Catchment. The community’s strong view is that an Eastern Terminal must not be built in P1 or P2 water catchment areas. The paper lists P1 catchment as ‘high impact’ and P2 as ‘medium impact’. P1 and P2 catchments must be ‘no go’ areas.
(b) Habitat protection/clearing impact. The paper lists total clearing
of more than 25 ha as ‘high impact’ and less than 10 ha as ‘low
impact’. The community’s view is that any substantial clearing of state
forest would be unacceptable. A substation could involve total clearing
of less than 10 ha – so it would be regarded as ‘low impact’! Any area in excess of 2 ha must be ‘high impact’. This must include clearing for transmission lines.
(c) Impact on existing businesses and residences; Noise and vibration. Any location closer than 2 km must be ‘high impact’.
Imagine what it would be like to have a switchyard, and possibly later
a substation, close to your house, orchard, vineyard or business.
(d) Impact on recreational areas such as picnic sites, parks, walking
trails and mountain bike trails. Only if the ET location is less than
500 m from such areas is the impact rated in the table as ‘high’. But
people walk into the forest from picnic areas. Any location closer than 2 km from such areas must be ‘high impact’.
(Incidentally, the site in Hacketts Gully that was selected by Western
Power in mid 2007 is traversed by the Kalamunda Circuit (a mountain
bike trail) and the Munda Biddi Track.)
(e) Reserved lands. National Parks are listed as ‘no-go’ areas. But
Regional Parks (eg Darling Range Regional Park) are ‘high impact’.
Regional Parks must be ‘no-go’ areas – for a switchyard/substation and
future transmission lines.
Location adjacent to a National Park or Regional Park, or within State
Forest, is rated ‘medium impact’. The very strong view of the community
is that all these areas must be rated ‘absolute impact’ ie ‘no-go’.
All these criteria are a matter of personal judgement. Please review
the table and make your own assessment – and comment accordingly.
Top of page
What comments should I submit to Western Power
As a minimum, we urge you to insist that:
- Open meetings are held as soon as possible, and well before
the closing date for submissions, to enable the community to be
properly informed.
- The comment period is extended to at least 2 months.
- Sustainability
principles are also applied to the question of whether an Eastern
Terminal should be located in this study area (ie not just cost and
technical factors).
- A complete review of the criteria listed
in Table 3.1 occurs, using community workshops to enable open
discussion of the criteria.
- Western Power publishes an accurate account of community members’ comments.
- And add your own particular concerns.