In The Press

Hills Gazette (16/08/08) Win for Power Protest

A group fighting the construction of an electrical switchyard in the Hills is celebrating after Western Power announced it would take the project back to the drawing board....

Read more...


Echo (16/08/08) Terminal discussed at meeting

Western Power's General Manager in Customer Services Mark de Laeter addressed the Shire of Kalamunda's Planning and Services Committee regarding the proposed Eastern Terminal switchyard. Over 80 people filled the chamber to demonstrate their disapproval of Western Power's lack of community consultation...

Read more...


Hills Gazette (July 2008) Walk Trail damaged

Western Power has admitted two of its contractors damaged areas of a walking trail in Kalamunda during recent maintenance.

Read more...


Hills Gazette (28/06/08) Substation in activists firing line

A newly formed group of Hills climate activists will fight the proposed construction of the eastern terminal electricity substation.

Read more...


Hills Gazette (28/06/08) Tsunami of salt is a real killer

...Lo and behold on the same page is a big advertisement - an invitation from Western Power. The subject is basically land clearing for its new power line.

Read more...


Hills Gazette (24/05/08) - Sparks fly over switch

Western Power have conceded they should have provided Hills residents with clearer information about the development of an Eastern Terminal Substation.

Read more...


Hills Gazette (19/04/08) - Fears over power plan

A group opposing Western Power's plans to build an eastern terminal substation in the Hills fear the community will not receive a fair hearing during the next round of consultation.

Read more...


Hills Gazette Letter to the Editor (19/04/08) - Why the change?

"I note with interest that Ian Buchanan from Western Power (Geologist's ideas rejected, Gazette, April 5) confirmed the southeastern terminal and the recommissioning of the transmission line are required in addition to the eastern terminal..."

Read more...


The West Australian (17/04/08) - Plan to build more coal power stations

Coal magnate Rick Stowe is planning to capitalise on the high price of domestic gas by spending up to $1.2 billion building 3 new power stations in a move that will put further pressure on the WA Government's greenhouse targets.

Read more...


Hills Gazette (05/04/08) - Geologist's idea rejected

Western Power has rejected a suggestion from a Hills Geologist that its planned eastern terminal substation is unnecessary.

Read more...


Hills Gazette (29/03/08) - Hacketts Gully plea

Kalamunda Shire Council wants the State Government to extend Kalamunda National Park to incorporate an area of the state forest at Hacketts Gully.

Read more...


Hills Gazette Letter to the Editor (29/03/08) - Residents must be consulted

"I am very concerned at Western Power's announcement of the building of a gantry on Mundaring Weir Road and upgrade of the existing 132,0000 volt line between Boddington and this new gantry."

Read more...


Hills Gazette (22/03/08) - Council speaks out on station

Kalamunda Shire Council has expressed its intense opposition to the area Western Power is studying as a site for a planned eastern terminal substation.

Read more...


Hills Gazette (15/03/08) - Calls to Delay Plan

A group opposed to Western Power's proposed eastern terminal substation in the Hills has urged energy minister Francis Logan to halt construction of a temporary gantry structure planned for Hacketts Gully.

Read more...


Hills Gazette (01/03/08) - Group to fight for land

Tourism operators in the Hills have joined forces to fight Western Power's plans to build an eastern terminal substation in the Hills.

Read more...


Hills Gazette Letter to the Editor (01/03/08) - Western Power plot thickens - Mr John Davenport, Bickley

"I note that Mr de Laeter claims the main reason for a "hills connection" to the metropolitan grid is because of new power stations being built at Collie".

Read more...


Hills Gazette Letter to the Editor (23/02/08) - Home not yet chosen for ET - Mr Mark de Laete, General Manager, Customer Services, Western Power

"In response to the letter from John Davenport from Bickley, published in the February 16 issue, I assure residents that Western Power has not chosen a location for the proposed Eastern Terminal (ET) substation."

Read more...


Hills Gazette Letter to the Editor (16/02/08) - Stealth at work over project - Mr John Davenport, Bickley

"Western Power's announcement of the reconstruction of the Collie to Hacketts Gully transmission line strongly suggests that it has chosen a site for the eastern terminal in the Hacketts Gully area."

Read more...


# Hills Gazette (09/02/08) - People power ignored

An action group fighting the construction of an electricity substation in the Hills believes Western Power has no interest in consulting the community over a site.

Read more...


Hills Gazette (15/12/07) - Substation put on backburner

Opponents to a proposed electrical terminal substation in the Hills have won a 12 month reprieve, with Western Power this week announcing it needs more time to consult the community.

Read more...


Echo Newspaper (14/11/07) - Shire seeks consultation

Kalamunda Shire Council will request a consultation with Western Power on the proposal for the new Eastern Sub Terminal.

Read more...


Hills Gazette (10/11/07) - Substation fight on

Opposition is mounting against Western Power's proposed Eastern Terminal Substation in the Hills.

Read more...


Echo Newspaper (10/11/07) - Terminal Call

Darling Range MLA John Day has called for the State Government to listen to concerns of local residents about a new terminal substation to be constructed in the Kalamunda District.

Read more...


Kalgoorlie Miner (Oct 07) - Threat to goldfields water

Goldfields drinking water could be at risk of contamination if a proposed Western Power substation is established in Kalamunda, according to Kalamunda Shire Councillor Frank Lindsay.

Read more...


Echo Newspaper (Oct 07) - Substation site up for discussion

Residents will take an active role in the selection of a site for a new $180 million terminal substation in the Kalamunda-Mundaring area, according to Western Power.

Read more...


Hills Gazette (29/05/99) - Substation opposed

Kalamunda Shire Council will "vehemently" oppose a bid by Western Power to build a substation near Mundaring Weir Road in Hacketts Gully.

Read more...


Western Power Announces Deferment of Hacketts Gully Line

by John Davenport 2/23/2010 3:05:00 PM

SETS Group welcomes the announcement by Western Power's Managing Director, Doug Aberle, that it has deferred work on the South-West bulk reinforcement project (the Boddington to Hacketts Gully line with associated gantry on Mundaring Weir Road).

Mr Aberle said a review had identified excess resources after it reduced the volume of capital works in the wake of the global financial crisis. It is regrettable that Western Power acknowledges the global financial crisis for this deferment rather than the unsuitability of the area for such structures. 

Consultation over the past 18 months has repeatedly drawn Western Power's attention to:

  1. the contravention of this project to the management principles for Priority One Drinking Water Source Areas,
  2. the variance to 7 of the 10 native vegetation clearing principles imposed by DEC,
  3. the excess of power in the SWIS system,
  4. the need to provide 'peak power' from generation sources close to the demand centres,
  5. the savings in peak power periods (27 percent) attained through 'demand side ' management,
  6. the reduced corridor width planned for the project which would expose our community to an increased risk of fire in an already fire-prone area
  7. the very real danger of the spread of die-back during the construction phase of the 90 kilometer line.

Western Power will update the community on April 28th with a community information session featuring Western Power's planning staff.

Watch for more details in the local press.

Be the first to rate this post

  • Currently 0/5 Stars.
  • 1
  • 2
  • 3
  • 4
  • 5

Tags:

Comments

2/18/2010 6:58:48 PM

Rita Sully

Thank you John. Yes, there are updates to share with the community in regards to the network infrastructure. We have tentatively scheduled April 28th for a community contact session however we are yet to confirm all the logistics. As soon as all logistics are confirmed we will promote the details through all available channels such as local media, letters, emails and our blog.

Rita Sully
Manager, Community Engagement and Sustainability Assessment

Rita Sully au

Comments are closed